Richard Morris
Group Head of Expert Witness Services – Time
Group Head of Expert Witness Services – Time
The judge in Downs Road Development LLP v Laxmanbhai Construction (UK) Limited [2021] EWHC 2441 (TCC), held that the adjudicator’s decision would not be enforced due to a breach of the rules of natural justice and highlighted the importance of the subjective requirement for a payment notice and pay less notice. The case possibly opened up a new path to “smash and grab” adjudications.
Downs Road Development LLP (“the Employer”) employed Laxmanbhai Construction (UK) Ltd (“the Contractor”) to demolish and erect new buildings containing 79 residential units. The contract was under an amended JCT Design and Build 2011 edition contract (“the Contract”). Clause 4 of the Contract provided that the Contractor was entitled to receive interim payments by way of periodic payments.
"The case possibly opened up a new path to 'smash and grab' adjudications."
"This case is an important reminder that paying parties should not submit a holding notice in the hope that it could buy more time."
The court found Payment Notice 34 failed to satisfy the requirement set out in section 110A(2) of the Housing Grants, Construction and Regeneration Act 1996 (“HGCRA 1996”), which requires a valid notice to contain:
“(i) the sum that the payer considers to be or to have been due at the payment due date in respect of the payment, and
(ii) the basis on which that sum is calculated;3
The judge noted that it was standard practice for the Employer to send two payment notices in each payment cycle.
The Employer did not show a sum “genuinely considered” to have been due together with the basis on which the sum is calculated. The sum was unrealistic, and the cover email clearly showed that Payment Notice was a holding notice to buy more time to make a fuller assessment of the Interim Application 34. Therefore, it was clear that the sum set out in Payment Notice 34 did not set out the amount the Employer actually considered to be due.
For the reasons above, the judge found that Payment Notice 34 was not valid.
"This case has possibly opened a new path to challenging the validity of payment notices or pay less notices."
The judge found the capping beam crossclaim was material to the dispute. He clarified material information is information that could potentially “make a significant impact on the overall outcome of the adjudication” 4
“Where the adjudication is concerned with a party's entitlement to be paid money, then a defence which would if successful remove that entitlement or diminish the sum to be paid will potentially be an issue in the adjudication.” 5
The crossclaim had the potential to reduce the sum payable to the Contractor. The adjudicator took a narrow view of his jurisdiction in thinking that it was to “take a snapshot of the position between the Parties at the time”. Regardless of what the outcome would have been, the capping beam defence was a matter to be addressed in the adjudication. Had the adjudicator decided on the capping beam issue, the Decision would have been unimpeachable.
By declining to address the Defence to which the Employer was entitled, there was a material breach of the requirements of natural justice; as such, the adjudicator’s decision could not be enforced.
The Employer contended that the conclusion the adjudicator reached before he found that the capping beam could not be considered, were unimpeachable as his reasons were separate decisions “not tainted by that error” 6; therefore, they argued that the Decision could be severed.
The court recognised that partial enforcement could be seen as compatible with the policy underlying the HGCRA 1996 and the Scheme for Construction Contracts (England and Wales) Regulations 1998 by allowing prompt payment of sums due, thereby maintaining cashflow in the industry.
The judge clarified that severance would depend on whether the decision is independent of each other or whether the adjudication contained “a series of decisions independent of each other or being a single decision resulting from a connected chain of reasoning.” 7 If the latter, severance is unlikely as it would involve “an artificial division of a continuous chain of reasoning” 8 and could result in an outcome that could not have resulted from the adjudication.
The adjudicator produced a snapshot of the position at a particular date to determine the sum payable in the payment cycle 34. The judge found that the adjudicator was not asked to make a series of separate decisions and reached a single decision. Severance of the Decision would be artificial.
For the reasons above, the court held that the Decision could not be severed; consequently, the entire Decision would not be enforced.
"The more evidence supporting the sum, the more difficult to argue that the payer did not have a genuine belief in the sum."
1 Downs Road Development LLP v Laxmanbhai Construction (UK) Limited [2021] EWHC 2441 (TCC) Para 20
2 Downs Road Development LLP v Laxmanbhai Construction (UK) Limited [2021] EWHC 2441 (TCC) [27]
3 S110A(2)
4 Downs Road Development LLP v Laxmanbhai Construction (UK) Limited [2021] EWHC 2441 (TCC) [53]
5 Downs Road Development LLP v Laxmanbhai Construction (UK) Limited [2021] EWHC 2441 (TCC) [54]
6 Downs Road Development LLP v Laxmanbhai Construction (UK) Limited [2021] EWHC 2441 (TCC) [90]
7 Downs Road Development LLP v Laxmanbhai Construction (UK) Limited [2021] EWHC 2441 (TCC) [92]
8 Downs Road Development LLP v Laxmanbhai Construction (UK) Limited [2021] EWHC 2441 (TCC) [92]
9 Bresco Electrical Services Ltd (in Liquidation) v Michael J Lonsdale (Electrical) Ltd [2020] UKSC 25
10 Bresco Electrical Services Ltd (in Liquidation) v Michael J Lonsdale (Electrical) Ltd [2020] UKSC 25 [47]